|
Sediment
traps, two-basin configurations, PAMs, and other strategies
By
Richard A. McLaughlin
The Balsam
Mountain Preserve development is a luxury residential
community on a 4,400-acre tract in the Little Tennessee
River Basin in Jackson County, NC. The tract had been
previously owned by Champion Paper Co. and had been
managed for wood production. The development plan includes
350 home sites of 2 acres each, an 18-hole golf course,
a practice range, stables with several pastures, and
several other amenities. More than 3,000 acres were
set aside as the Balsam Mountain Trust, which will be
preserved as a conservation easement for recreational
use by residents. The preserve has 38 miles of streams,
15 miles of which are considered permanent. The development
occurs on the western side of the tract with most potential
impacts occurring on Sugarloaf Creek and Cashie Branch.
The purpose
of this project was to work closely with the preserve
developer to install and evaluate a variety of erosion
and sediment control systems to reduce the movement
of sediment into surface waters. Workshops to introduce
these practices to developers, contractors, and public
agency staff were held periodically as the systems were
tested and evaluated. Three sites were monitored for
portions of the project time period, and the results
are discussed by site.
Sports
Garden Site
This 6-acre area was cleared and grading was initiated
in early 2003. Steep slopes had to be graded to provide
level areas for tennis and other amenities. Two sediment
basins were installed in series to detain runoff. The
first basin had several configurations (Figure 1) before
the final construction with a perforated riser and stone
outlet (Figure 2 ). A sampler was first installed in
the riser barrel, but it was discovered that the infiltration
rate in the basin exceeded the runoff inflow rate in
most storms so the water never rose to the barrel elevation.
The sampler was then moved to the deepest point in the
basin to provide the greatest chance of obtaining samples
(Figure 3 ). However, this sampler proved very unreliable
and tended to obtain samples during periods when no
flow was occurring. As a result, many of the samples
had very low turbidities because the sediment on Balsam
Mountain tended to settle fairly quickly after each
storm.
The site
was stabilized with grass in May 2003 as further grading
was postponed, although the channels that carried runoff
to the basin were not stabilized so erosion in them
continued.
The water
exiting the upper basin flowed down a steep, rock-lined
ditch to a culvert under a gravel road and into a second,
much smaller basin (Figure 4 ). This basin had a permanent
pool of 2 to 3 feet and a rock spillway. Some of the
water entering this basin came from the roadside ditch
above the culvert. We installed a V-notch weir in the
spillway crest in order to measure flows out of the
basin. Two samplers were also installed, one at the
culvert and one at the outlet. A logging rain gauge
was installed adjacent to the basin.
This two-basin
design, with most of the heavy sediment being removed
in the first basin, facilitates the use of polyacrylamide
(PAM) in the second basin. This was attempted initially
by inserting PAM logs into the culvert pipe under the
road; however, this proved problematic in that the reduced
flow capacity in the pipe backed water up over the road.
The two logs were removed from the pipe and placed on
the rock splash pad below the pipe outlet.
The sampler
in the upper basin obtained samples from four storms
in the May through July 2003 period. The first three
resulted in very low turbidities and probably reflect
low runoff amounts (Figure 4). The last storm sampled
had very high turbidities, occasionally exceeding 8,000
nephelometric turbidity units (NTU). Rainfall records
from nearby Cullowhee indicate nearly 3 inches of rain
over the three-day period of July 1 through 3. The average
turbidity was 5,600 NTU for this last storm, compared
to around 400 NTU for the previous two storms. It is
possible that the intake of the sampler was too close
to the basin bottom and was sampling sediment settling.
When these samples were allowed to settle overnight
in the lab, the average turbidity was less than 30 NTU.
Erosion was
evident on the site until grass was established in the
late summer of 2003 (Figure 5 ). In addition, water conveyances
continued to erode even after the site was fully vegetated
(Figure 5 and Figure 6 ). This is common on active construction
sites, and one recommendation would be to encourage
the use of inexpensive materials in water conveyances
to reduce erosion.
Average turbidity
for the May 5 through 9, 2003, event at the entrance
to the sports garden was 911 NTU, while for the exit
it was 186 NTU (Figure 15). This indicates that there
was some treatment during this period, possibly as a
result of the PAM logs, because flow was relatively
low. Higher turbidities in later storms with higher
flows indicate that the PAM logs were ineffective and
that the second basin had sufficient turbulence to prevent
significant settling (example in Figure 16). Turbidity
in these samples usually dropped two orders of magnitude
when left on the lab bench overnight, indicating that
velocity and turbulence were too high in the small basin
to settle material efficiently.
Overall,
we would recommend that frequent, heavy use of mulches
and vegetation be used on sites similar to the Sports
Garden site because the steep slopes can erode quickly
as the grading progresses. Ditches should be stabilized
using check dams and lining with geotextiles. Sediment
control at the Sports Garden site was problematic due
to the difficulty in creating enough sediment basin
area on this steep slope. The installation of the two-basin
system worked well for smaller storms, but turbidities
were still high during high-flow rates.
Stables
Site
The stables and associated pasture encompassed
5 acres of clearing adjacent to Cashie Branch. All of
the site was graded to drain away from the creek and
into a 4,000-cubic-foot sediment basin. We recommended
the use of a flashboard riser outlet, which was installed
in March 2003 (Figure 7 ). This was installed in a manner
similar to a perforated riser, placed away from the
dam wall and with a stone collar due to the contractors
unfamiliarity with this type of outlet. More specific
instructions to install it closer to the dam wall and
anchored to the bottom with stakes or cement were needed.
The purpose of the flashboard riser is to allow the
formation of a permanent pool while retaining the ability
to drain the basin if needed to remove sediment.
Most of the
area was well stabilized with grass and mulch when grading
was complete, but a fill area for the stables continued
to contribute sediment to runoff for several months
(Figure
8 ). The first attempt to reduce this impact was
to install a small sediment trap below the disturbed
area (Figure
9 ). While this did retain a large amount of the
sediment, the water was then released on the pasture,
creating more erosion (see Figure
8 ). The sediment trap was reconfigured as a skimmer
basin with the outlet connected to the stabilized, rock-lined
ditch that led to the sediment basin (Figure
10).
(Figure
11)
The first
recorded rain event (February 22, 2003) had the highest
turbidities, all greater than 1,000 NTU.
This event occurred prior to the installation of baffles
in the basin and before seeded grass had time to emerge.
Jute/coir baffles spread the flow of water across the
whole basin decreasing the turbulence and velocity of
the water, and optimizing the settling potential of
the basin (Figure 12). All subsequent runoff events
had turbidities less than 1,000 NTU. Sediment loads
leaving the site were calculated using total suspended
solids (TSS) measurements from the collected samples.
The February 22 rain event had a sediment load of 1,940
kilograms in approximately five hours, higher than a
later rain event (May 5 through 9, 2003) of longer duration
and higher peak exit flows (2 to 3 cubic feet per second,
versus 1 to 2 cubic feet per second for February 22),
which lost 354 kilograms. Turbidities fluctuated with
flow, averaging 220 NTU.
This site
went through a typical series of runoff events. The
first events after clearing and grading had high sediment
loads, but as the site became more stabilized the runoff
water quality improved greatly. The primary sediment
basin appeared to function much better with the rock
checks and porous baffles that were added. The attempts
to reduce turbidity by introducing PAM logs in the ditches
were not successful because the logs tended to either
get buried under sediment or dry out and become inactive.
There is evidence that PAM logs were somewhat effective
in the flashboard riser barrel, where they remained
moist and did not accumulate sediment.
Practice
Range Site
The Practice Range site is approximately 20 acres,
which were cleared in the summer of 2002 (Figure 13).
Runoff coming on to the site was redirected into drainage
pipes to a point below the cleared area. A number of
temporary sediment traps were placed around the site
during the initial grading. These tended to have very
high infiltration rates. During one storm, we witnessed
water running into these traps, which were essentially
excavated pits, with no water leaving them and no visible
rise in water level. The site is apparently underlain
by a landslide debris field and as a result has very
high infiltration rates.
The final
design consisted of three basins (B1, B2, and B3), one
emptying into the next before water exits the site near
Sugarloaf Creek. Automatic samplers were placed at the
entrance to B1, at the exit of B1 (entrance to B2),
and at the exit of B3, along with several single-stage
samplers.
The first
challenge was the inlet channel into B1, which collected
runoff from the disturbed area above the basins. It
emptied into the basin near the outlet, allowing the
runoff to directly exit the basin with no settling time
for the sediment. Silt fence and coir log diversions
were installed to guide the water toward the front of
the basin to allow full use of the basin and two jute/coir
baffles. The outlet for B1 was a flashboard riser leading
into B2, which also contained two jute/coir baffles.
The final basin, B3, had one baffle. Two manufactured
channel check dams, GeoRidge (Nilex Inc.) and Triangular
Silt Dike (Triangular Silt Dike Co. Inc.), were placed
in the channel leading into B1, while geotextile material
was used under the rocks in the spillway between B1
and B2. PAM logs (APS 706) were placed in the flashboard
riser to treat the turbid water as it passed into B2.
On July 25,
2004, the area received more than 6 inches of rain in
approximately 8 hours. As the channel leading into B1
eroded, the sampler and rain gauge were washed out,
not collecting any entrance samples. The first basin
filled with sediment, burying the baffles (Figure 14 and Figure 17), and B2 also filled with sediment to the top
of the baffles (approximately 4 feet high). Much of
the rock in the spillway between B1 and B2 was displaced,
but the underlying geotextile material prevented additional
erosion from occurring. The sampler at the exit of the
site below B3 recorded turbidities of 80 to 260 NTU,
suggesting the majority of the eroded sediment was kept
onsite. Following this event, site maintenance included
digging out the deposited sediment; constructing a new
channel, which was re-routed to enter B1 at the front
end (farthest away from the outlet); and replacing baffles.
September
had three hurricanes pass through the area, dumping
more than 12 inches of rain on the site for the month.
Turbidity data collected from the September 7 through
9 event shows an increase in turbidity from the entrance
of B1 (range 380 to 5,940, average 1,900 NTU) to the
exit of B1 (range 130 to 10,700, average 3,390 NTU). This probably does not accurately represent
the entire event, as the entrance sampler collected
only eight samples before the intake line was buried
beneath sediment. Turbidities leaving the site ranged
from 180 to 1,800 NTU and averaged 420 NTU with a calculated
sediment load of 1,006 kilograms from the TSS measurements.
Through the
fall of 2004 the site continued to have grading on the
middle to upper slopes. Most of the runoff was still
being directed into the first basin using the diversion
ditch. However, this ditch had eroded badly due to the
heavy rains in September and is probably the source
of much of the sediment now filling the first basin
(Figure 18). We recommended that this ditch be reworked
and lined with geotextile because it appeared it would
be in place for some time to come.
A ground
cover demonstration was completed, including pine needles
and an excelsior erosion control blanket (Curlex from
American Excelsior Co.) in comparison to the tub grinder
mulch and hydraulically applied wood fiber used onsite
(Figure 19 ). Although we did not collect extensive data
from these plots, we did observe that runoff collected
in the tubs below plots treated with PAM at 20 pounds
per acre was noticeably clearer.
Richard
A. McLaughlin, Ph.D., is an associate professor in the
Soil Science Department at North Carolina State University.
EC
- November/December 2005
|