An
examination of downchutes for stormwater runoff at a
South Dakota mine site
By
Mike Jacobs, Anne Rotter, Tim Cazier, and Paul Clopper
Cellular
articulated concrete block (ACB) systems are flexible
concrete revetments used to resist the erosive forces
of flowing water resulting from elevated velocities
and wave action in concentrated flow areas. A typical
ACB revetment mat is formed by interlocking precast
concrete blocks placed on a geotextile fabric. The interlocking
matrix allows versatile structure design for use over
varying land contours and grades. ACBs traverse changes
in terrain without disrupting the placement patterns
and interlocking features of the system, allowing for
partial settlement of the underlying foundation without
disrupting the integrity of the installation.
 |
| Interlocking
ACB matrix |
The blocks
within the (mat) matrix are dense and durable, and the
resulting revetment is flexible and porous (Abt 2001).
Voids between blocks allow vegetation to establish over
time, decreasing flow velocities and improving final
appearance.
ACBs became
part of the erosion protection arsenal within the past
15 years. In 1999, a hydraulic testing protocol was
developed to ensure that each block system will satisfy
users' design needs for stream and river stabilization
(Leech 1999). Results of testing these protocols have
been published (Abt 2001).
This article
describes the performance of an ACB system under rugged
conditions, steep slopes, and exposure to intense rainfall.
The site is the Richmond Hill Mine, located in the Black
Hills of South Dakota. The mine is part of reclamation
efforts undertaken by Lac Minerals LLC. This site was
chosen for study because it has several steep downchute
channels protected by ACB, and because several storm
events equal to or larger than the design storm event
have occurred since downchute construction. The ACB
system constructed at this site is Tri-lock produced
by American Excelsior Inc.
To provide
some reference for long-term performance of this relatively
new engineering product, the article describes the field
performance of the downchutes that have already experienced
several extreme storm events, specifically:
- Localized
erosion (causing a 'bridging' effect) under block
connections and between the geotextile and ground
surface; and
- Concrete
cracking and fracturing under extreme weather conditions
or during long-term exposure.
Background
The Richmond
Hill Mine is located in western South Dakota in an area
that receives an average of approximately 40 in/yr of
precipitation. Golder Associates developed a surface
water management plan for the property that included
a reclaimed overburden stockpile (ROS). Stormwater runoff
is conveyed off the ROS in steep downchute channels
armored with Tri-lock.
The ROS contains
five downchute channels constructed in 1994. Three of
these downchutes were inspected by the authors in 2001.
Downchutes 1 and 2 are located on the south-facing slope,
intercepting runoff from vegetated bench channels at
regular intervals. Downchute 3 is on the northwest-facing
slope. Specific downchute design parameters are outlined
in Table 1.

All downchutes
on the Richmond Hill site are armored with ACB and designed
to convey runoff from the 100-year, 24-hour storm event
of 4.8 inches (Hershfield 1962) and withstand the 100-year
design storm event intensity of 1.4 inches of rain in
about 25 minutes. (Golder 1997).
Tri-lock
lock-and-key blocks are manufactured from 4,000 lb/in2
(psi) concrete (AEI). Initial block-production efforts
yielded blocks prone to surface chipping and cracking,
causing the onsite construction contractor to increase
concrete strength parameters. A concrete strength of
approximately 4,600 psi was ultimately selected from
results of laboratory testing and provided intact individual
lock-and-key blocks. The downchutes investigated in
this study are armored with Tri-lock blocks casted from
4,600 psi concrete.
Installation
 |
| The
downchute conveys stormwater runoff from the Richmond
Hill overburden stockpile. |
The first
step in ACB installation is preparing the foundation.
Site preparation is important to ensure adequate performance.
The American Excelsior design manual states: 'Before
placing the Tri-lock system, the slope shall be inspected
to insure that it is free from obstructions such as
tree roots, projecting stones, or other foreign matter.
Voids or other soft areas should be filled with suitable
materials and well compacted. Although some variation
in contour will be allowed, no sudden changes in level
can be accepted' (ErosionWorks 1996). This recommendation
was adopted at Richmond Hill.
Once the
ground surface has been prepared, the geotextile filter
fabric is placed. The lock-and-key blocks are transported
to the site and manually placed in an interlocking fashion.
Finally, the voids are partially backfilled with topsoil
to permit vegetative growth.
Extreme
Events
October
1994. On October 5, 1994, Richmond Hill experienced
almost 7 inches of rainfall in less than 20 hours (LAC
Minerals 2001). Heavy rainfall continued into October
6 but was not recorded because the storm caused a power
failure at the site, disabling the rain gauge.
May
1995. In May 1995, the property experienced
an even higher intensity storm, when nearly 9 inches
of rainfall were recorded within a 24-hour period (LAC
Minerals 2001). This event nearly doubled the predicted
100-year design event.
July
1997. On July 31, 1997, 2.04 inches of rain
fell in 25 minutes. The design storm intensity used
for the ACB downchutes for this duration storm is 1.4
inches of rain (LAC Minerals 2001). In addition, 'This
event was preceded by significant rainfall during the
prior week, which increased antecedent moisture conditions.
The structures performed extremely well and only minor
repairs were required' (Golder 1997).
June
1998. On June 17 and 18, 1998, Richmond Hill
experienced 6.97 inches of rain in approximately 20
hours (LAC Minerals 2001). During the storm, 2 inches
of rain fell in less than one hour.
Calculations
The authors
performed hydrologic modeling using the May 1995 storm
event of 9 inches in 24 hours as a means to gauge the
field conditions in the three downchute sections. Results
are listed in Table 2.

During this
storm event, the downchute sections experienced significantly
higher velocities and nearly double the shear stresses
of the design parameters listed in Table 1.
Observations
 |
| Downchute
channel protected by ACB |
A four-person
inspection team consisting of one representative of
site management and the authors of this article performed
a site investigation, including a detailed inspection
of the downchute areas. Notable features included blocks
displaying stress cracks after installation. The inspection
team performed tests (with a metal probe) between the
lock-and-key blocks to determine the presence of voids
below the blocks approximately every 10 feet along the
downchute length.
Overburden
Stockpile Downchute Channels
Beginning
on the overburden stockpile, the inspection team examined
the downchute channels from the uppermost bench location
(initiation point of the ACB portion of the downchute).
The downchutes investigated in October 2001 were installed
in 1994. The upstream end of the Tri-lock mat was not
anchored, but the sides of the downchute mat were anchored
into the overburden stockpile cover material. Investigations
focused on the blocks in the downchute bed. Site personnel
noted that the 4-inch blocks were laid directly onto
the geotextile and the open space between blocks backfilled
with topsoil. Visual inspection indicated a good vegetative
cover including 12-inch-high grasses in the downchute
bed. In fact, much of the Tri-lock mat was obscured
due to the dense cover.
 |
| Typical
sideslope termination with sides of mat anchored
into the stockpile |
 |
| Typical
installation process |
Between the
first and second bench, the mat was more visible. The
geofabric was intact and resistant to penetration with
a sharp metal probe. The open spaces between the blocks
displayed good vegetative cover. Few cracks and no block
breakages were observed. One spot of bridging was observed:
a 2-inch-diameter void space between the geotextile
and underlying rock. The void was a half-inch depression.
Immediately above the second bench channel, the first
crack was observed in a key block. Continuing down the
first downchute channel, the inspection team observed:
- One broken
lock block adjacent to one broken key block approximately
20 feet downstream of the final bench channel. The
blocks, though broken, were clearly still locked into
the Tri-lock mat matrix and were not protruding above
the mat surface. Vegetation was rooted in the crack
between the broken pieces; and
- One cracked
key block approximately 50 feet from the downstream-most
end of the downchute channel.
The
northwest downchute channel (Downchute 3) is the steepest
of the downchutes at approximately 2.5H:1V. The mat
is notably less uniform in this section, and the blocks
display more cracks. One broken and one cracked key
block were found approximately 5 feet from the bottom
of the downchute. All blocks in this section (including
the damaged blocks) remained locked into position and
remained a functioning part of the mat system. The inspection
team was unable to dislodge even the protruding blocks
using the metal probe as a lever.
While testing
approximately every 10 feet down the downchute, the
probe did not reveal any other voids below the block
mat or any voids between the geotextile and underlying
prepared surface.
Three protruding
blocks were noted on the second downchute. The protruding
blocks were not accompanied by voids and were not dislodged
by probing with the metal lever. This downchute channel
also contained a cracked block directly upstream of
a 1.5-foot-diameter boulder lying in the downchute bed.
At one location in this downchute the inspection team
noticed an area marked by several broken and cracked
blocks. There was an apparent 'hole' in the mat and
a 2-inch void beneath one of the broken blocks. Mouse
droppings surrounded the area, and the inspection team
concluded that the mice caused the voids and perhaps
compromised the integrity of the base material, causing
additional stresses in this location. Nevertheless,
the blocks in this area were not dislodged or protruding
above the plane of the mat. Site personnel indicated
the condition at this location was first noticed after
the intense storm in 1997. Field inspection after the
storm noted that the blocks remained securely in place.
Summary
 |
| Vegetation
cover in the bed of Downchute 3 |
Of all of
the ACB downchutes inspected, site personnel indicated
that only one block had been 'tamped back down into
place' during a routine inspection of the downchute
channels on the waste dump surface since installation.
Overall,
less than 1% of the blocks investigated were cracked
or broken, and in the areas showing stress cracks or
fractures, less than 10% of the surface area was affected.
The damaged blocks remain in place and function as part
of the ACB erosion prevention mat.
Conclusions
Observing
and documenting the condition of installed ACB products
is an important means to understanding field performance
and provides valuable information for future design
applications. The conclusions from this study are these:
Tri-lock
system integrity is stronger than the integrity
of individual blocks because the system can function
properly even in areas marked by cracked and broken
block pieces. The pieces remain a part of the mat, held
in place not only by the interlocking nature of the
product but also by backfilled and deposited soil and
the root systems of established vegetation. Because
each block interlocks with its neighboring blocks, it
forms a total membrane, 'allowing the entire revetment
to act as one' (ErosionWorks 1996).
Good quality
assurance on foundation preparation is critical
for long-term durability of the mat systems. Continuous
contact between the ground surface and the geotextile,
and between the geotextile and the blocks, allows the
system to function optimally.
Channel
slope is a factor in the durability of ACB systems
as shown by downchute sections that experienced the
same volumes of water: Higher velocities in the steeper
channel sections (2.5H:1V) caused more stress cracks
and block breakages. Nevertheless, the mat remained
intact and the channel functional through the extreme
storm events. Localized failure in the downchute bed
did not cause failure of the downchute system during
the storm events experienced.
Natural
forces other than rainfall events, such as boulders
moving down the downchute bed and debris flows or invasive
animal activity can also cause damage to the ACB mat.
Again, fractures and block breakages caused by such
occurrences did not cause failure of the mat system.
As concluded
in the studies related to ACB testing protocol, 'Stream
bank or embankment stability is directly linked to the
interaction of the block foundation, filter, block size,
block void space, block weight, and degree of articulation'
(Leech 1999). Field reports support these findings and
further provide evidence of the longevity and stability
of articulated concrete products despite experiencing
storm events where total rainfall and rainfall intensity
were higher than design values.
References
Ayres
Associates (formerly Resource Consultants and Engineers).
1993. Hydraulic Stability of Trilock 4010 Revetment
in High Velocity Flow. Performed for the Am. Excel.
Co., Ayres project No. 92-0857, February. Fort Collins,
CO.
Abt,
S.R., J.R. Leech, C.I. Thornton, and C.M. Lipscomb.
2001. Articulated Concrete Block Stability Testing.
Journal of the American Water Resources Association
(37):1.
Clopper,
P.E. 1989. Hydraulic Stability of Articulated Concrete
Block Revetment Systems During Overtopping Flow. US
Department of Transportation, Federal Highway Administration.
Pub. No. FHWA-RD-89-199. Virginia.
ErosionWorks
Version 1.0 [software package and reference manual].
1996. American Excelsior Company - Earth Science Division.
Golder
Associates Inc. 1997. Final Report Construction Quality
Assurance Monitoring and Test Results: Excavation, Soil
Liner, and Related Construction for Reclamation of Heap
Leach Pads No. 1, 2, and 3. Lakewood, CO.
Hershfield,
D.M. 1962. Rainfall Frequency Atlas of the United Sates
for Durations from 30 Minutes to 24 Hours and Return
Periods from 1 to 100 Years,' (USWB Technical Paper
40) Washington DC: US Weather Bureau.
LAC
Minerals. 2001. Personal Communications with Richmond
Hill Mine Personnel and Electronic Rainfall Records.
Richmond Hill Mine, Lead, SD.
Leech,
J.R., S.R. Abt, C.I. Thornton, and P.G. Combs. 1999.
Developing Confidence in Concrete Revetment Products
for Bank Stabilization. Journal of the American Water
Resources Association (35):4.
Mike
Jacobs, P.E., is a principal and Anne Rotter, P.E.,
and Tim Cazier, P.E., are project engineers with Golder
Associates Inc. in Lakewood, CO. Paul Clopper, P.E.,
is manager of Water Resources for Ayres Associates in
Fort Collins, CO.
EC
- July/July 2004
|