|
Erosion
and sediment control practitioners talk about the impact
of Phase II and the techniques they're currently using.
By
Carol Brzozowski
With Phase
II of the National Pollutant Discharge Elimination System
(NPDES) in effect, the challenge for engineers, contractors,
and developers now is to determineand put to usethe
best methods for controlling sediment at a job site.
According
to Arthur Miner of A.J. Garrett and Associates, an erosion
control company in West Des Moines, IA, sediment control
has come a long way in the past few years yet still
has a long way to go. "The people who should be
involved are taking it much more seriously," he
says.
While some
municipalities are tightening up sediment control measures,
others still seem to be sitting on the fence.
"Now
that we have Phase II kicking in, I'm seeing operations
as usual, and that is too bad," says Jerald Fifield,
president of HydroDynamics Inc. in Parker, CO. "We
can have a Phase II, a Phase III, and a Phase XX, and
if we don't have anymore enforcement out there, passing
all of these additional laws isn't going to matter at
all.
"The
changes are beginning. Smaller municipalities are starting
to pass rules so they don't have [the Environmental
Protection Agency] coming down on them. It's fine to
pass rules to protect the environment, but if we're
passing these rules, we'd better be ready to enforce
the rules and have qualified inspectors and people who
know what they're looking for so we all can work together
to minimize the amount of sediment pollution sites."
Fifield,
who has written extensively about sediment control,
points out a distinction: Dirt is what leaves an original
site, and sedimentation is dirt causing problems because
of where it ends up.
"There
is erosion control, there is sediment control, and then
there is sedimentation. There are big distinctions.
Sediment is particles suspended in runoff water that
vary in size and shape and are a result of erosion that
has occurred due to rainfall or other means."
Fifield notes
that sediment control methods have been relatively ineffective
for most suspended particles, except for particles "that
are like large spans and have a heavier mass."
One technique
used to deal with sediment in runoff is flocculation.
"You add polyacrylamide [PAM], and it chemically
bonds together suspended clay particles to make them
larger so you can get a deposition to occur," explains
Fifield. "It is usually introduced as water is
flowing to, say, a sediment containment system. It can
also be introduced on hillsides, although the research
is still out as to the effectiveness."
Fifield says
the biggest drawback to using PAM effectively is that
it has to be mixed with water and takes a lot of "tender,
loving care" to make it work right. In addition,
the wrong PAM can be detrimental to fish life downstream.
When PAM is introduced, it increases the size and weight
of the particles and can start developing an effective
sediment containment system. The correct PAM is not
toxic to fish.
Still the
most effective sediment control measures are effective
erosion control practices, Fifield says. "Essentially
you have to do erosion [control] as you're doing the
construction process, compared to erosion control at
the end of the construction process, which is different.
Fortunately contractors and developers are finding out
that implementing erosion control practices as the construction
activities occur can be done in a cost-effective manner."
Aicardo Roa-Espinosa,
an urban conservationist with Dane County Land Conservation
in Wisconsin, notes that the goal of a sediment control
plan is to deal with the problems on-site and that control
and strict inspection help cut down on potential problems.
He also is experienced with the use of flocculants for
sediment control. "We don't want soil loss to become
sediment. Once you have sediment, you have to clarify
the ponds of sediment with the use of coagulant and
flocculent. It has to be a chemical treatment. And it's
very difficult."
Roa-Espinosa
says Dane County is the only one in the country using
a coagulant and flocculent for water clarification.
He has developed a control measure using PAM.
Practices
vary throughout the country on what is being used for
sediment control. Miner's company previously used primarily
silt fence for sediment control but now advocates other
measures, such as berms, blankets, and matting, to provide
the most efficiency for the dollars invested.
Miner, a
former Department of Transportation employee, does a
great deal of work for the state, county, and city transportation
departments. "The state is very serious about making
[sediment control] effective, and that feeds down to
counties and cities," he says. "They'll listen
to our suggestions, but they have very stern policies
they want to follow, and we have to bid accordingly."
For example,
the company put in compost on 15 ac. of land and then
applied a wood-fiber hydroseed mixture on top of it.
"It's kind of extreme, but it works for controlling
sediment," he says. "It was a steep slope
on a freeway grading project that went into a river.
We've used hydroseeding and hydromulching to keep sediment
out of the river."
One of Miner's
company's most challenging sediment control jobs involved
a project near the Des Moines River. "The slopes
were incredibly steep with loose soil, and we had to
try to stop it," he notes. The company laid down
erosion matting and hydroseeded mulch. As it was a steep
area, silt fences were placed adjacent to the other
measures taken.
Sales Manager
Corey Simonpietri of Landsaver in Richmond, VA, says
his company has changed its practices to become more
proactive in the services it provides. Landsaver, which
handles a variety of erosion control projects, is a
division of ACF Environmental.
Although
the company has installed best management practices,
with the contractor agreeing to maintain whatever was
done, it is getting an increasing number of requests
from clientsespecially large homebuilding companiesfor
a regular system of inspections.
"They
don't necessarily want to know every in and out, every
code, and every regulation that has to be maintained
on a site. They're looking for somebody who can help
them do that," Simonpietri says.
Landsaver is employing a variety of methods for sediment
control, including Gutterbuddys, silt fences, erosion
control blankets on drainage ditches during mass grading
projects, and check dams or silt dikes in small drainage
ditches.
The company
is experimenting with silt dikes for truck entrances,
especially downhill entrances, "so you can run
over them and not restrict access but at the same time
keep the sediment from flowing out of the site,"
says Simonpietri.
Ron Jueneman
is with R.L. Jueneman Construction in Hanover, KS, a
company that works extensively for the state in providing
seeding, silt fencing, and erosion control blankets.
He uses silt fence in areas under construction, and
if the area needs ponding, he'll do that too. Circumstances
dictate how Jueneman approaches sediment control.
"With
a silt fence, if you try to use it like a pond dam,
it won't work. You need to put it in at intervals so
it has a chance to keep the water slowed down and put
it in on a gradient basis so it works similar to a terrace
channel. If you try to put it in just at the bottom
of a big hill and expect it to work, it won't. It's
not designed for that, and it isn't big enough."
It works better on areas where there is a dike with
an inlet pipe through it, he adds.
Jueneman
concedes that silt fences have a bad reputation. "Guys
just hurry up and slop it in incorrectly. States don't
want to pay for too much silt fence because it's just
a temporary deal." He believes NPDES is likely
to change that approach.
In Santa
Rosa, CA, Ron Powers's Fedco, a general engineering
firm, provides earthwork, grading, paving, and sewer,
water, and storm drain construction. Powers has seen
more stringent sediment control measures in effect as
a result of Phase II, with sites being inspected more
frequently. He says the regulations have created a "mini-industry"
of sorts.
"More
developers are requiring that we do at least the initial
installation of the erosion control; there are few subcontractors
who specialize just in that. Those who do are usually
very busy, so we generally have to hire a few more people
in order to do that. We ask the developer to take over
the maintenance," Powers says.
His company
is on the lookout for devices that are easier to install,
are more effective, and thus reduce violations of regulations.
His company uses KriStar Flo-Gard and other products,
such as rice-straw fiber rolls, which are confined in
nets and used for slopes and perimeter sediment control
in lieu of silt fence. The rice-straw fiber rolls are
easily installed and maintained and filter the water
better, Powers says.
The company
also uses Slope-Gard 3, a curled, aspen-wood excelsior
fiber roll, around catch basins or curb inlets in lieu
of sandbags and hay bales. Powers says it not only slows
down the flow, but it also filters the sediment better
than sandbags and hay bales do and is easier to handle.
"You don't prefill sandbags; you have to bring
sand and bags to the job and fill [the bags] and then
get rid of the excess."
Fedco also
uses catch-basin inserts. "A lot of sediment is
generated during construction, and that really helps
keep the new boxes and pipelines clean," Powers
says. "You're not getting a lot of floatation down
into the storm drain system during construction. Although
they are a postconstruction device, we encourage owners
to put them in early and be proactive, rather than reactive,
to the regulations."
Lisa Reas
of L.J. Reas Consulting in Green Lake, WI, has been
involved in shore stabilization efforts at a creek that
runs through Middleton, WI, where a lot of erosion has
occurred. "We're seeing the state [Department of
Natural Resources] become much more particular on various
types of erosion control," she says of the Phase
II era. "All of the municipalities are being very
particular with it."
Her company
does shoreline restoration and erosion control projects,
and her specialty is bioengineering. She often uses
BioLog by ACF Environmental.
Reas believes
everyone now is catching up to what should have been
going on all along. "People are becoming more aware
of the state funding for erosion control projects and
shoreline restoration projects, whereas people used
to feel you had to come in and just throw rock on shorelines
to provide stabilization."
Many counties
have developed erosion control practices and have on
staff someone whose job it is to review them, Reas says,
adding, "Contractors are really being forced to
tow the line on this." Wisconsin is proactive in
bringing contractors and county officials together "to
talk about what products are out there, how they have
been used, how they're going to be used in the future,
what we've done wrong, and what is the right way of
doing it.
"It's
going to be a couple more years before we really have
this down as far as what needs to go where and what
our best uses of resources are going to be."
Yet Miner
observes more people developing erosion and sediment
control plans. "When [NPDES] first came into effect,
engineering consultants really weren't too sure what
to do. Now they do a very good job."
For an example
of what municipalities are doing in response to NPDES,
consider Dane County, which has established standards
exceeding those of NPDES Phase II, says Roa-Espinosa.
He explains that the county's water-quality standards
are linked to such factors as the steepness of a slope
and the amount of time a construction site will be open.
The county
requires contractors to fill out a plan showing a site
diagram with a legend of influencing factors, such as
the property line, gravel access, vegetation, existing
and planned storm sewers and inlets (or culverts), and
drainage and planned erosion control methods. The plan
is detailed with respect to erosion control practices:
- The county
requires that soil storage piles be contained by a
downslope sediment fence or covered with a tarp and
recommends that they be located more than 25 ft. away
from any downslope road or drainageway.
- Temporary
gravel access drives must have 2- to 3-in. aggregate
stone laid at least 7 ft. wide and 6 in. thick. Drives
must extend from the roadway 50 ft. or to the building,
whichever is less.
- Sediment
controls must minimize the amount of eroded soil leaving
the site and be installed along the down-slope sides
of the disturbed areas unless permanent seeding and
mulching are planned to be completed within 30 days
of the start of grading. Sediment controls must be
installed around soil storage piles, inlets, and outlets
and along adjacent drainageways that receive site
runoff.
- Contractors
must provide information on location of practices
that will be used to control erosion on steep slopes
with a grade greater than 12%.
- Contractors
must provide information on the location of sediment
barriers around storm sewer inlets.
- Areas
of concentrated flow must be diverted properly around
disturbed areas. The county recommends that overland
runoff from adjacent areas greater than 10,000 ft.2
be diverted around disturbed areas in a manner that
will not adversely impact adjacent landowners. Diversions
must be stabilized with seeding and mulching within
24 hours of diversion completion.
- Drainageways
must be stabilized with seeding, mulching, and other
appropriate measures within 24 hours of drainageway
completion. Sediment controls must be installed at
the outlet ends of drainageways.
The plan
also is detailed with respect to management of erosion
control:
- Rough,
graded, disturbed areas planned to be left inactive
for more than 30 days and temporary soil stockpiles
planned to be left inactive for more than seven days
are to be stabilized by temporary seeding between
April 1 and October 15 or by other cover, such as
a tarp or mulching.
- Permanent
seeding must be completed by September 15, or sodding
must be placed by November 15. Straw or grassy-hay
mulching is recommended for all disturbed areas planned
for seeding. The contractor must list the permanent
seeding type and rate of application.
- Downspout
or sump-pump outlet extensions to stabilized areas
are to be used.
- Sediment-laden
discharge should be ponded temporarily behind a sediment
barrier until most of the sediment settles.
- Building
material waste is to be disposed of properly as to
avoid pollutants and debris being carried off-site
by wind or water.
- Erosion
control practices will be inspected daily and must
be maintained in working condition.
- Accumulated
sediment must be removed from behind sediment fences
and barriers before it reaches a depth equal to half
the barrier height. All sediment that moves off-site
due to construction activities must be cleaned up
by the end of the workday. Sediment that moves off-site
due to a storm event must be cleaned up at least by
the end of the next day, if not earlier. Temporary
gravel access drives must be maintained throughout
construction in working condition. All erosion control
practices will be maintained until the disturbed areas
they protect are permanently stabilized and established.
The set limits
ensure that those who do not do anything beyond the
time of seeding and mulching lose their permit. "You
have to go back and do it again, and we will collect
our money. Or you risk being red-tagged, and you lose
the permit. Either way, you lose the permit," Roa-Espinosa
says.
Dane County
does not accept silt fences as erosion control. "If
you show up with silt fences in this office, you have
to go back to the drawing board. You have to use berms,
mulch, and seeds, or you can sod. We are also implementing
putting in an inch of compost mixed with polymers as
a sediment control and seeding establishment. Everything
grows so beautifully because it's organic matter."
Roa-Espinosa
has developed formulas for sediment control based on
a PAM mix. He uses a different mix for water clarification.
Particles will settle faster because the pond must be
retained for six hours.
"By
doing that," Roa-Espinosa explains, "the particles
attach to the other particles by the polymers, and by
the mix of the coagulants, the flocculent, and then
the aggregates, the sediment in suspension becomes bigger,
and then it goes down faster. Then you have less sediment
going through the outfall of the pond, detention basin,
swale, or site."
Roa-Espinosa
says a plan is useless unless there is frequent inspection.
"If there is no good inspection, it doesn't matter.
You can have a beautiful plan on paper, but then you
have to follow up. You must have a date when you are
going to begin, when you are going to seed, and when
you are going to finish. There's maybe one extension
we give for 30 or 40 days, but if you are not done,
then you lose the permit."
Miner sees
a more serious attitude toward erosion control since
Phase II, with more effective methods being employed.
His company now is spending twice as much time inspecting
and maintaining sediment control measures. "We're
trying to concur with the requirements," he says.
"When [a silt fence] gets half-full or more, we
clean it out and keep an eye on it to make sure it's
not leaking. Even if there aren't leaks in the silt
fence, we're looking for problems that we can stop before
they get started."
Proper installation
and maintenance are critical for preventing problems.
"The most important part of a successful plan is
to maintain it," Roa-Espinosa says. "If the
builder or developer is careless, it doesn't matter
how wonderful the product is you will have sediment
coming out."
Miner agrees.
"If you don't do it right the first time, you lose
ground immediately. If you don't get your silt fence
in the ground deep enough and staked up, the water will
get under it. That's the biggest problem. We put everything
in the ground a footthe state requires it. We
probably still have some leakage problems, but you can
minimize it."
Simonpietri's
clients sometimes call the company to say a sediment
control method is not working. "We look at it,
and it's not that it's not working; it's that it's not
been maintained. Once sediment has clogged something
up, it's obviously not going to work."
Some of Landsaver's
clients handle maintenance on their own; many "just
don't want to have to think about it," Simonpietri
says. "They want to know that when the inspector
shows up on the site, it's done, and they're not going
to have anything to worry about."
Landsaver's
time invested in maintenance varies. "In Virginia,
the code is that you have to inspect it every two weeks
and then after a rain event. We're finding that if we
finish a job early, we can get out and look at one or
two of our sites and knock out those inspections, make
sure everything is working, and then react quickly when
we do find a problem," Simonpietri relates.
Jueneman
uses straw bales but prefers silt fence for its ease
of installation and maintenance. "It needs to be
put in there deep enough and packed in there tight enough
so water can't get underneath it," he says. "You
need more stakes at the bottom where it's criticalotherwise
the water will push it overand then fewer stakes
as it goes out. Cutting corners doesn't work. It's got
to be put in the right way, or it won't do any good
at all."
Jueneman
says silt fences should be maintained on an as-needed
basis. "You don't have to get carried away with
it, but you need to be there and check them after a
big rain, get the silt dug back out of them, and get
them stapled or staked back up. If you've got a spot
that didn't work, you need to do something different
with it, like put in an extra fence or a sediment basin."
His clients
usually maintain the fence themselves. Not much maintenance
is needed during a dry season, but when there are heavy
rains, inspection occurs usually once or twice a week.
Powers has
a different take on silt fence. "You've got to
put a trench down," he says. "You've got to
make sure it's catching the sediment. But it tends to
fall over because it's not as strong a product. The
rice-straw fiber rolls hold up far better and look nicer.
When you've got a lot of rainfall and you've got a silt
fence up and it's really done its job, it starts to
look kind of ratty. Not that it doesn't work, but these
new devices are much easier to handle, and we get feedback
from inspectors that we get cleaner runoff at the bottoms
of the slopes where the water ultimately ends up running."
KriStar has
a maintenance division that cleans out inserts, Powers
explains. "They're proactive in the postconstruction
insert field by making sure that the owners know they
also have to maintain these things. That's an issue
coming up with the mandates, that the future owners
of the commercial properties have to maintain whatever
is installed. The mandates are getting more strict in
that they're going to be inspecting these sites on a
yearly basis and sometimes biyearly."
Fifield stresses
that it is very important to know when to install certain
measures. "When you first begin a project, hopefully
the designer has put down a set of plans of what they
are going to put in before they start moving material
so everybody knows what's going on before it gets done,"
he says. "The weakest link is not the contractor.
The weakest link is the inadequate plans that designers
are providing contractors."
A postconstruction
plan should identify what erosion and sediment control
methods to remove after construction. "You don't
leave the silt fence in there forever; you've got to
get rid of it. That has to be clearly identified,"
Fifield says. "The designer should be out there
continually checking the measures to see that they were
installed correctly and if there was a failure why it
occurred and whether the method needs to be changed.
"More
importantly, we do some type of maintenance that involves
repairing and/or replacement of what failed, and we
do that in a very timely manner," Fifield says.
"EPA says we [must] do it within seven days, but
we try to do it as quick as possible, especially when
you're in an area that has a lot of chances of rain
falling. The maintenance issue is very critical, and
the correct installation is extremely critical."
Thomas Carpenter
of Carpenter Erosion Control in Ankeny, IA, points out
that daily maintenance issues center on repairing devices
that have been knocked down or moved for some reason,
and operational maintenance is about replacing or duplicating
once the sediment device has done its job and is now
full of sediment.
"For example, most specifications call for cleaning
a silt fence when it is half-full," he says. "But
the question is how to remove it and what to do with
it. It just creates another problem. My belief is to
leave it stored behind the device and build a new one
to collect new runoff."
Planning
and budgeting of materials required for an erosion and
sediment control plan is usually done on a per-linear-foot
basis, industry specialists say, and the final costs
depend on products used. But those costs are nothing
compared to the fines levied for not using the methods.
Fines and
penalties can be hefty for violations, such as not controlling
sediment that leaves a site or improperly maintaining
sediment control measures.
Roa-Espinosa
says the most severe penalty for a violation is a stop-work
order. "That hurts. There's a lot of machinery
and workers they're keeping on it. That hurts more than
any fine. We only fine people in extreme cases. If you
stop a guy from working two or three days of the week,
he really pays the price."
Roa-Espinosa
says the county has found stop-work orders to be very
effective because there are companies that get fined
and still continue their same practices while paying
the fine. Powers concurs, pointing out that a stop-work
order can be even worse than a fine because it has a
synergistic effect that impacts everyonefrom the
worker to the developer.
In Powers's
area, those who violate regulations get warnings, with
subsequent fines ranging from a few thousand dollars
up to $10,000 for a repeated fine.
Fifield says
the Clean Water Act stipulates that violations for negligence
carry a fine of $2,500$50,000 per day of violation
or one to two years in prison, with $50,000 fines reserved
for repeat offenders.
"Knowing
violations"acts done purposefullyresult
in a range of fines from $5,000 to $100,000 per day
of violation and/or three to six years in prison. "Knowing
dangerous" is a violation that can result in a
$250,000$1 million fine and/or 15 years in prison
for a particular incident.
The fine
for making a false statement on an inspection report
is $10,000$20,000 and/or two to four years in
prison. EPA has an administrative penalty that carries
a daily fine of $10,000$25,000. A Class-Two administrative
penalty ranges from $10,000 to $125,000 a day.
Fifield says
"deep pockets" are being hit with significant
fines, including many departments of transportation
in Tennessee, Idaho, and California. EPA has made inspections
nationwide and levied more than $1 million in fines
against 12 entities because they did not have plans
on-site.
Many people
with the CPESCCertified Professional in Erosion
and Sediment Controldesignation, such as Carpenter
and Fifield, or with similar certifications, find that
it provides them with more clout. Simonpietri, who is
not a CPESC and says Virginia does not do a lot with
the CPESC program at this point, is in the process of
becoming a certified inspector in Virginia. "It
basically helps me talk in the same terminology they
know, and the training background is similar. I've been
in erosion control for more than 10 years, but that
doesn't always mean anything to somebody who's on-site."
Fifield believes
that because of their training and background, CPESCs
often are more qualified than engineers. "It doesn't
mean that an engineer doesn't know how to do it, but
the regulatory people are making a huge mistake by saying
only engineers sign plans. My opinion is that there
ought to be a qualified person to sign plans, and if
that turns out to be an engineer, fine. But if it turns
out to be a CPESC, then that person ought to be able
to sign the plans."
Fifield says
there needs to be more communication and cooperation
among designers and contractors on ensuring that the
rules are followed. Contractors need to know that the
cost of erosion and sediment control "is going
to be cheap compared to the cost to clean up everybody's
mess on their properties and fight off all of the fines
that are going to come down on you."
Frequent
contributor Carol Brzozowski is a journalist in Coral
Springs, FL.
Click
here to order or find out more on Jerald Fifield's
books,
Field Manual on Sediment and Erosion Control Best Management
Practices for Contractors and
Inspectors, and Designing for Effective Sediment and
Erosion Control on Construction Sites.
EC
- March/April 2004
|